How to create a basic PM and have it run on a schedule?

Overview:

This guide explains how to configure an automated process that generates Work Orders based on a time schedule using the Automations menu (which includes PM, PdM, and more).

Getting toAutomations and entering basic PM details

STEP 1: Go to Automations (PMs+) Module. Click New PM.

How to go to automations & new PM

Start by clicking on the main menu button on the left panel, top left portion.

Shows clicking on the Main Menu button

If the menu button isn't visible, you are likely on a screen too narrow to see everything, press on the left pointing gold button to take you so you can see the menu button.

Shows the gold button to get to the panel containing the main menu button

Variation 1: What you have access to

Depending on the size of your screen, what products your company has purchased and what rights you have been granted, the choices in the menu will vary.

Variation 2: How wide your window is

The menu will show up as 1, 2 or 3 columns depending on how wide your screen is.

If you are on a cell phone, and some smaller tablets in portrait mode or a narrow window on a laptop or desktop, you'll see the menu as one column that you scroll through using your finger or the scroll wheel or the scroll bar depending on your device, browser and whether you have a touch screen or not.

Narrow window shows as one column

A bit wider, some cell phones in landscape, some tablets in portrait, most tablets in landscape and 'somewhat' wider laptop/desktop, will show it as 2 columns wide, with the middle column available on the left by scrolling down

Shows 2 column wide menu

And wider screens, some landscape tablets, and wider windows on a laptop or desktop show it as 3 columns. If you have all the dropdown sections expanded, it may still require vertical scrolling to see all the choices depending on the height of your device or window.

Shows the 3 column menu layoutShows the PMs+ Automations module with the option to create a new Preventive Maintenance (PM).

STEP 2: Enter the basic PM details

How to enter basic PM details
  • ID (Depending on your system configuration, the ID may be hidden or generated automatically.)
Shows the button to fill up the necessary information.
  • Name
Shows ID and Name that is based on user preference.
  • Asset

Navigate to the Asset tab to add an asset.

Shows asset tab

Click the green circle with plus (+) sign button to add a new asset.

Shows add an asset

Click the three-dot button to select an asset.

Shows to add asset

Click the green circle with plus (+) button to select a child asset. The list displays the available parent assets. Scroll through the list and select the desired child asset.

Shows to pick an asset.

Upon clicking the asset, the child assets under the parent asset Calgary are displayed.

Shows child asset.

In this example, I selected Edmonton, specifically [EDM - Coast Terrace Inn], as my asset.

Show a choices to click for a parent asset.Show a choices to select a child asset under parent asset.

STEP 3: Scroll to the Trigger or Schedule Section

Select 'Schedule Trigger'.

Shows how to select a Trigger Type.

STEP 4: Choose the frequency:

- Daily - Weekly - Monthly - Yearly

In this section, I selected "Every Day" and configured the trigger to run at 1:00 A.M., 2:00 A.M., 3:00 A.M., and 4:00 A.M.

Shows to modify schedule trigger.

Notice that, like in the entire system, when you create a new child item such as the meter above, the striped background shows it is still pending. When you click on the save?The save button used in millions of applications is an image of a floppy disk where we saved files in the 1970's through 90's (2020's in Japan), it became the de facto save button for that reason. button it is made a 'real', not pending, record.

Shows save button.

STEP 5: Add Plan of Action

Go to the Plans / Actions tab of the PM.

Shows Plan/Action button.

Click the Add New Action button.

Add New Action Button

Choose the action type:

  • Create Work Order – the PM will automatically generate a Work Order when triggered. It will ask you to specify the procedure.
See here for more information on the Create Work Order
  • Run Event – the PM triggers a configured Event instead of creating a Work Order. Events are system-defined actions created and managed in the Automations/Event setup area.
See here for more information on the Run Event Shows to add new action. Shows add name and procedure. Shows the entire procedure.

Step 6: Monitor The PM History

Since the PM is scheduled to run at 1:00 A.M., 2:00 A.M., 3:00 A.M., and 4:00 A.M., you could verify if it executed correctly by checking the History section.

Go to the History tab of PM.

Look for log entries showing each scheduled run time.

Confirm that:

  • The PM triggered at the correct hour.
  • A Work Order or Event was created (depending on the action selected).

If no entries appear, the PM did not run — recheck the schedule, activation status, or settings.

History (Before)

Shows History.

History (After)

Shows the history record.